Ahrens
Enterprises
Albertville, Minnesota
Trucking company headquarters (office, warehouse, maintenance & storage
yard)
Architect: Rosa Architectual Group, Russ Rosa
The Challenge: Having been displaced by a City eminent domain procedure,
Russell
Delivery was left without a home. An unfulfilled commitment from another contractor
to get them into a new facility created further frustration. A site was ultimately
located, but the expiration of a short-term lease at an interim facility required,
without exception, occupancy of a
new facility by January 1st.
The Olson Solution: Project team members were assembled who were all committed
to achieving the project’s schedule and budget objectives. Early meeting
with City staff led to swift approval from Planning and Council. Advance commitments
to key materials suppliers were significant in ultimately meeting the owner’s
objectives. Careful site planning minimized
costs
associated with troublesome site characteristics. The finished project is not
only meeting the owner’s current needs, but also allows that space planned
for their future expansion be leased out and generate additional income in the
interim.
|